Project

STRAND BRIDGE HOUSE

138-142 Strand, Paddington, London WC2 R1HH
Client
Job cost
£200k
Scaffold size
1,092
square meters
JOB DURATION
40 weeks
The refurbishment of this office building required us to provide scaffolding support…beginning on the fourth floor with planners adding an additional floor the structure.

With the rest of the property being occupied by tenants and a high density of London traffic and footfall, health and safety issues occupied a great of our planning.

The rear elevation was installed off a designed cantilever truss from the fourth floor and above. A 28.0m gantry was added to the Strand elevation supporting a passenger hoist off gantry and a beam hoist at one end of the gantry.

A pedestrian management and exclusion zone was set up after consultation with local authorities and the client.

"This was a project that was time-important. The building had clients waiting to move in so the clock was ticking from the moment we were contracted by Tolent. I am delighted to report that our team were up to the challenge, especially considering the complexity of designing and installing a scaffolding structure from a cantilever truss at fourth floor level."
Gary Silke
Texo Scaffolding Operations Director